vee wood gas projects
Investing in a sustainable future
We have successfully implemented and commissioned several wood gas projects in recent years. Each project is individually managed by us according to your requirements and framework conditions.
For detailed information and visits to our references, we look forward to hearing from you.
Plant Willibald Höllmüller GmbH
AT / Lower Austria
Operation of timber mill and green electricity generation
The company operates a sawmill, planing and glulam plant with associated pellet production. The challenge was that the existing biomass boiler did not provide enough thermal energy to dry the sawdust required for pellet production.
The aim was therefore to replace the boiler, ensure a constant heat supply and also open up a new business area by generating electricity from wood chips. With the VEE wood gas plant, it was possible to achieve exactly that: reliable, economical and designed for continuous operation. The thermal output of 600 kW covers the pellet plant as well as the planing hall, drying kiln and residential building. In addition, 350 kW of electrical energy is provided as a full feed-in.
- Systems
1 x wp3.350
- Date of commissioning
July 2025
- Electrical output
370 kWh
- Thermal output
650 kWh
- Fuel: Standard wood chips
Sattledt plant, Vorchdorf local heating
AT / Upper Austria
District Heating Network & Green Electricity
Nahwärme Vorchdorf, a cooperative of 42 farmers, has been operating the biomass heating plant in Sattledt for five years. Due to the energy crisis and rising prices for fossil fuels, a new heating plant was built together with the municipality of Sattledt and Raiffeisenbank. The aim is to switch to a renewable heat supply.
The plant supplies 4,400 kW of thermal and 500 kW of electrical power. The electricity is generated around the clock using wood gas, and an additional 900 kW of heat is produced. Together with the old stock, 550 households can be supplied with heat and 1,440 with electricity.
This means that the entire municipality of Sattledt – excluding industry – can be supplied with COâ‚‚-neutral energy in future.
- Systems
2 x wp3.250
- Date of commissioning
July 2025
- Electrical output
500 kWh
- Thermal output
930 kWh
- Fuel: Standard wood chips
Gräsalp biomass heating plant
AT / Vorarlberg
District Heating Network & Green Electricity
The Gräsalp biomass heating plant is relying on vee technology to expand the district heating network in the municipality of Schoppernau.
The district heating network has a length of approx. 3 km and 70 connections, supplying heat to hotels and businesses as well as the municipality and private households.
The new vacuum technology is being used for the first time in wood chip drying. The dryer is encapsulated, dust formation in the installation room is very low and the dryer achieves maximum efficiency with minimum power consumption.
- Systems
1 x wp2.150
- Date of commissioning
Dec. 2024
- Electrical output
160 kW
- Thermal output
290 kW
- Fuel: Standard wood chips
Nordwald Energie GmbH
AT / Lower Austria
District Heating Network & Green Electricity
Nordwald Energie is active in the business field of eco-energy generation and the operation of a district heating network using vee synthesis gas systems.
The district heating network has a length of approx. 8 km and 145 connections, with a total connected load of 3,500 kW. It is operated with 2 buffer storage tanks, 48,000 liters each, and a wood chip boiler for winter use.
There is one existing drying system with a capacity of 400 kW th for wood chips, sunflowers, corn, grain, e.g. and a new drying system with a capacity of 900 kW th for wood chips.
- Systems
2 x wp3.250
- Date of commissioning
Oct. 2024
- Electrical output
500 kW
- Thermal output
930 kW
- Fuel: Standard wood chips
Nahwärme Vorchdorf e.Gen.
AT / Upper Austria
District Heating Network & Green Electricity
In 2022, the expansion project of the heating plant, the new wood gas plant, was put into operation.
The heating plant in Vorchdorf supplies around 900 single-family homes with heat. The wood gas plant generates electricity for around 850 single-family homes.
- Systems
3 x wp2.150
- Date of commissioning
June 2022
- Electrical output
480 kW
- Thermal output
870 kW
- Fuel: standard wood chips
Ă–ko Energie Zauner
AT / Upper Austria
Waste Disposal and Operation of District Heating Network
The company has been operating a biogas plant for years and is active in waste disposal, biomass drying and the production of organic fertilizers. The wood gas CHP system is in operation since June 2022.
The district heating network in the Pettenbach area has a connected load of > 3MW; the consumers are private households and commercial enterprises.
- Systems
2 x wp2.150
- Date of commissioning
June 2022
- Electrical output
320 kW
- Thermal output
580 kW
- Fuel: standard wood chips
Reference system 300 kW
AT / Vorarlberg
Due to high demand for plants with higher output, the development of a wood gasifier with a combustion capacity of approx. 1 MW and a CHP with an electrical output of approx. 300 kW began in 2018. The prototype was commissioned in 2021.
From this development, the sizes wp3.250 and wp3.350 are available as standard in the meantime.
- Systems
1 x wp2.300
- Date of commissioning
February 2021
- Electrical output
300 kW
- Thermal output
600 kW
- Fuel: standard wood chips
2020
AT / Vorarlberg
Biomass Facility
- 1 plant wp2.150
- biomass drying process
- electric power generation
2022 and 2019
CH / Montreux
Agriculture and Forestry
- 2 systems wp2.050
- facility heating
- hay drying
- electric power generation
2019
DE / Bavaria
Eco Energy
- 1 plant wp2.150
- District Heating Network & Green Electricity
- electric power generation
2018
DE / Bavaria
Eco Energy
- 1 plant wp2.150
- biomass drying process
- electric power generation
2018
AT / Vorarlberg
Brickwork Company
- 2 plants wp2.150
- brickwork drying process
- electric power generation
2018
DE / Black Forest
Woodwork Company
- 2 plants wp2.150
- exchange of palm oil CHPs for woodgas CHPs
- timber drying
- electric power generation
2017
DE / Allgäu
Agriculture and Forestry
- 1 plant wp2.050
- wood chip drying
- facility heating
- electric power generation
2014
AT / Vorarlberg
Woodwork Company
- 1 plant wp2.150
- 1 plant wp2.050
- reference plants at the vee owners woodwork company